Announcement:
Please can all motorists in Stowmarket follow the set diversion routes currently in place. These are here for your safety during your gas main replacement work.
Welcome!
This is your designated page offering you all the information about the gas mains replacement happening in your area. Stay up to date on the latest progress with weekly updates. You can also see more about what to expect by going to our Cadent Local tab!
Check in next week where you can see what's coming up next in your area.
Your Project
Start Date: 28th October 2024
End Date: February 2025
Our teams will be providing essential work in Stowmarket. The 15 week upgrade will involve phased road closures with access for residents remaining throughout . Our work is set to begin on Monday 28th October and will be completed by end of February 2025.
We will be working across Tavern Street, Finborough Road, and Recreation Road. Installing tough new pipes which will last for decades, future proofing the Stowmarket network.
6 January 2025 at 16:00:00
Our teams are now back on site!
We hope you all had a great Christmas and a happy new year.
To start the new year our teams have begun work on Recreation Road. To conduct our works safely, there will be a road closure in place on Recreation Road, this closure will be moving along the road in three phases. Lasting until the 24th of January. There is also two-way traffic lights on the junction of Recreation Road and Violet Hill.